When the five-year land lease ends, this building moves with its owner. This 45 m demountable clear-span steel exhibition hall in Ivory Coast is engineered to be unbolted for relocation. Xinguangzheng fabricated the 4,725 m² pavilion for an events venue operator on a leased waterfront parcel in Abidjan’s Port-Bouët Exhibition Corridor. A 48-day ex-works production cycle preceded shipment, and handover closed on January 12, 2026. Its first trade expo followed three months later, in April 2026.
| Project Parameter | Project Specification |
|---|---|
| Client Sector & Region | Events venue operator, Port-Bouët Exhibition Corridor, Abidjan, Ivory Coast |
| Building & Footprint | 45 m clear span × 105 m long × 8.5 m eave, 11.2 m ridge; 4,725 m² single story |
| Structure & Foundations | 100% bolted demountable portal frame on reusable precast concrete pier blocks |
| Steel & Coating | S355JR / Q355B welded H-sections, hot-dip galvanized with powder topcoat for C4 exposure |
| Envelope & Rigging | 60 mm cam-lock acoustic PIR panels; certified 1-ton rigging eyes, 0.40 kN/m² design rigging load |
| Design Codes & Wind | NF EN 1991 / EN 1993; coastal wind 120 km/h |
| Shipment & Lead Time | 224 tons of steel and cladding, 11 × 40’HQ containers, CIF Autonomous Port of Abidjan; 48-day ex-works cycle |
| Delivery & First Event | Handover January 12, 2026; first trade expo April 2026 |
A Five-Year Waterfront Lease Rules Out Poured Foundations
The client’s business model sets the structural brief: the operator leases an urban waterfront parcel for five years. The building must be able to relocate intact when the term comes up for renewal. A conventional portal frame fights that requirement in two ways. Cast-in-place concrete footings are difficult to lift out and reuse, and typically end as buried demolition waste. Site-welded connections cannot be undone without cutting steel, so dismantling becomes demolition work. Fabric marquees sidestep heavy foundations but fail the functional brief. The brief calls for insulation against Abidjan’s heat and rain-noise control for event audio. Export geometry adds a further constraint, because a 45 m clear span means each half-rafter runs about 22.7 m along the slope. The project container packing limit was 11.8 m per piece. The rafters therefore had to ship in segments and bolt together through splices built for repeated assembly and dismantling.
Friction-Grip Rafter Splices Sized for 40’HQ Containers
Design started in Tekla 3D, and cutting began only after the client signed the model. The rigid frame steel building system uses welded H-section portals in S355JR / Q355B steel. All modules are hot-dip galvanized and powder-coated for the coastal salt atmosphere. Each half-rafter ships in segments of no more than 11.7 m, with end plates pre-welded in the shop. The 8.5 m columns travel as single pieces within the same container limit. Site crews join the segments with 10.9S high-strength friction-grip bolts in M20 and M24 sizes. The preloaded bolts clamp the shop-welded end plates together. Interface friction resists shear, while the tension-side bolts and plate bearing carry the rafter bending moment. Crews weld nothing on site, and disassembly needs no torch cutting. Certified 1-ton rigging eyes were fabricated into the central-bay rafters for LED video walls and line-array speakers. The frame is designed to NF EN 1991 / EN 1993 for 120 km/h coastal wind and a 0.40 kN/m² rigging load.

Packing followed the standard export routine with one addition:
- Steel pallets and loading plan: structural bundles were strapped to custom steel pallets against a per-container loading plan.
- Reusable transport cradles: purpose-built steel cradles shipped with the same consignment, retained on site for future relocation cycles.
The 224-ton shipment of steel and cladding filled 11 × 40’HQ containers. It departed the Port of Qingdao on CIF terms to the Autonomous Port of Abidjan.
Recoverable Pier Blocks and Bolted Column Bases on Site
Rather than cast-in-place footings, surface-recoverable precast concrete pier blocks carry the bolted column bases. The blocks sit at grade, lift out at lease end, and leave the ground recoverable. Supply responsibility was split clearly: our engineers issued the pier block layout and the column-base interface details. The owner’s local team precast the blocks, prepared the ground and set them in position. The same team erected the steel and installed the envelope in accordance with our Tekla installation drawings. The concrete blocks were therefore local scope, outside the 224-ton steel and cladding shipment. This kept wet trades and crane work local, while every interface dimension stayed under design control. After the short drayage from the Autonomous Port of Abidjan to the Port-Bouët parcel, erection proceeded bay by bay. The completed pavilion reached formal handover on January 12, 2026.

Cam-Lock PIR Panels and Certified 1-Ton Rigging Eyes
The roof and wall envelope had to be demountable too. Through-fixed sheeting risks tearing when it is stripped, so the design uses 60 mm acoustic PIR roof and wall panels with cam-lock and concealed-clip fixings. The cam-lock and concealed-clip fixings allow panel removal without pulling fasteners through the facings. The insulated acoustic envelope is designed to reduce tropical rain noise and air-conditioning demand. Both targets address event acoustics during downpours and the running cost of a cooled hall. Overhead, the certified 1-ton rigging eyes across the central bays serve the 0.40 kN/m² design rigging load. Rigging crews distribute truss loads across multiple eyes, so no single eye works beyond its 1-ton rating. Air-conditioning, stage lighting and audio, LED screens and trussing were owner-procured. Our delivery covered the demountable steel shell, the quick-lock envelope and the certified rigging points.
First Expo Loads and the May–July Rainy Season
The first trade expo in April 2026 put the rigging design to work.

The hall then operated through Abidjan’s main rainy season from May to July 2026. Those peak downpours are the design case for the roof’s rain-noise damping and cam-lock weather seals. The hot-dip galvanized steel and powder topcoat protect the frame in Port-Bouët’s salt air.
Unbolting the Hall: Relocation Boundary and Quote Scope
At lease end, relocation runs the erection sequence in reverse:
- Envelope: release the cam-locks, remove the concealed clips and stack the PIR panels for reuse.
- Frame: undo the friction-grip splices and lower the rafter segments and columns as shipped modules.
- Transport: repack the modules onto the reusable steel cradles that arrived with the original containers.
- Ground: lift the precast pier blocks for reuse and restore the parcel surface.
The system suits semi-permanent commercial metal buildings on leased land where local precast supply and crane access exist. It suits trade fairs, concerts and corporate events within the 120 km/h wind and 0.40 kN/m² rigging design envelope. A permanent campus with decades of fixed tenure, or heavy industrial crane duty, is better served by cast-in-place foundations with embedded anchor bolts and heavy permanent framing. If you operate on leased ground, send your parcel dimensions, lease horizon and event rigging schedule. We will return a demountable frame layout, a pier block plan and a container count you can budget against.